Refineries

Project - Augmentation of Bitumen Blowing Unit Capacity (Biturox Technology) in Mathura Refinery, India

FEED and Basic Engineering, Detailed Engineering, Project Management, Construction Supervision, Commissioning Assistance

The facilities covers the Augmentation of Bitumen Blowing Unit capacity with Biturox Technology to enhance the capacity from 500 TMT/ Year to 750 TMT/ Year, which involves Replacement of reactor internals, modification of incinerator and knockout drums and procurement services

Client - Indian Oil Corporation Limited, India

Engineering Schedule – 12 Months

Project - Propane Recovery Unit and Associated Facilities, Oman

Verification of Basic Engineering, FEED for Propane Recovery Unit which includes Mounded Pressurized LPG Storage Bullets, LPG transfer & Dispatch facility and associated Utility & Off-site.The facilities covers:

ISBL with Propylene Recovery Unit & utilities ,OSBL includes storage & pumping facilities - Two existing mounded bullets (Capacity:1040 T each) are designed for LPG/propylene,Pumping and Transportation facilities.

Client - Oman Refineries and Petrochemicals Company, Oman

Engineering Schedule – 6 Months

Project - Motor Spirit Quality Upgradation 

Residual Process Design and Detailed Engineering Services (Multi-disciplinary) for Hydrogen Generation Unit for the Motor Spirit Quality Upgradation Project

The facility covers the Design of Hydrogen Generation Unit (Capacity of 60 MMTPA) of Haldor Topsoe Technology

Client - Daelim, Korea

Engineering Schedule – 12 Months

Project - New Flare Gas Recovery at Mina-Al-Ahmadi (MAA) Refinery, Kuwait

FEED Endorsement and Detailed Engineering (Multi-disciplinary) for flare gas recovery

The facility includes Flare Gas Recovery Unit and associated facilities designed to handle a total flare gas load of 4,500 Nm3/hr and separating into gas and liquid. Primary aim to recover both standard flare gas and acid flare gas from their respective vent and flare systems and recycle back to the MAA refinery fuel gas system via the HSR (Hydrogen Sulfide Recovery) Units 50 & 90.

Client - Gulf Spic, Kuwait

Engineering Schedule – 6 Months

PROJECT - SULPHUR RECOVERY UNIT (SRU)

Residual Process Design, Detailed Engineering covering all disciplines, HAZOP/ SIL study, Procurement Assistance, 3D modeling, etc. The facility includes:

New Sulphur Recovery Unit (SRU), Tail Gas Treatment Unit, TGTU & Sulphur Yard (2 x 80 TPD), New Amine Regeneration Unit (ARU) (500 TPH), New Sour Water Stripper Unit (SWS) (220 TPH)

Client -Confidential - India

Engineering Schedule – 18 Months

PROJECT - LPG Amine Absorber System in PFCC Unit

Engineering, Procurement and Construction Management (EPCM) Services, Detailed Engineering (Civil, Structural, Architectural, UG piping, Mechanical, Piping, Electrical, Instrumentation, Insulation, Painting, Assistance in obtaining statutory clearance) , Procurement Services, Inspection & Expediting, Construction Supervision, Start-up, Commissioning and performance test for new / revamped equipment, final documentation .

The facility covers for Installation of LPG Amine Absorber System in PFCC Unit

Client: Mangalore Refinery & Petrochemicals Ltd., India

Engineering Schedule – 33 Months

PROJECT - Continuous Catalyst Regeneration Revamp.

Engineering, Procurement and Construction Management (EPCM) Services, Detailed Engineering (Civil, Structural, Architectural, UG piping, Mechanical, Piping, Electrical, Instrumentation, Insulation, Painting, Assistance in obtaining statutory clearance) , Procurement Services, Inspection & Expediting, Construction Supervision, Start-up, Commissioning and performance test for new / revamped equipment, final documentation for Continuous Catalyst Regeneration (CCR) Regeneration Revamp Project.

client: Mangalore Refinery & Petrochemicals Ltd., India

Engineering Schedule – 33 Months